Overview
Monday, July 14, 2026
QuickBooks
Updated 4:47 PM
6
Active projects
4 GC · 2 Sub
$42.5K
Invoiced — Jul 2026
Across all projects
$55.2K
Vendor balance due
2 accounts overdue
139 hrs
This week (timeclock)
Employees: 52 hrs
Subs: 87 hrs
Project Financials
Revenue
Builder cost
Vendor Balances
Active Projects — Schedule
View all ↑↗
Project
Dec '25
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Johnson Public Library
GCCP
TODAY
Johnson Public Library · Dec 2025 → Oct 2026
Harger
GCTM
Harger · Feb 2026 → Dec 2026
French 1
SUBTM
French 1 · Jan → Sep 2026
French 2
SUBTM
French 2 · Jan → Sep 2026
Camp Johnson
SUBTM
Camp Johnson
Gomez Renovation
GCCP
Gomez · Jun → Oct 2026
Upcoming Meetings
Open Calendar ↗
July 2026
Su
Mo
Tu
We
Th
Fr
Sa
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
2:00 PM
Tuesday
Jul 15
JPL OAC Meeting
School St, Johnson VT
9:00 AM
Thursday
Jul 17
VOSHA Site Inspection
Johnson Public Library
8:00 AM
Friday
Jul 18
Site Walkthrough — Gomez
Hardwick, VT
Punch List
Johnson Public Library
Interior finishes12
Exterior / site8
MEP & systems5
25 open items
Spruce Peak Punchlist
Units24
Common areas6
30 open items
Gomez Renovation
General3
3 open items
Tasks
Bid Pipeline
Duggan's Row
GC · BHA · $450,000 est.
In Review
Due Jul 25, 2026
Bunting-Cresap
Sub · New West BC · $85,000 est.
Estimating
Due Jul 20, 2026